330 kV Cable Outer Sheath Fault Location: A and C Phase Sheath Faults on a 100 m Buried Cable

2026-11-25

latest company case about 330 kV Cable Outer Sheath Fault Location: A and C Phase Sheath Faults on a 100 m Buried Cable
01  /  Summary

At a Glance


330 kV
System voltage

100 m
Route length

3
Fault locations


Cable type Single-core armored cable; outer sheath testing
Fault type Sheath-to-ground faults on phases A and C
Insulation readings 0 MΩ at 500 V DC on the outer sheaths of both phases
Fault locations Approx. 40 m on phase A and 43 m and 90 m on phase C, measured from the test end
Methods used Insulation resistance testing, step-voltage pinpointing, DC sheath withstand testing
02  /  Problem

The Problem

A 330 kV single-core armored cable, approximately 100 m long, was found to have sheath-to-ground faults on phases A and C. An insulation resistance test at 500 V DC gave readings of 0 MΩ on the outer sheaths of both phases, indicating severe sheath-to-ground faults rather than minor insulation leakage. The cable is direct buried less than one metre deep and the route was known, but one cable termination was located on a tower outside the substation fence while the other was inside the station. Since the station-side termination was inaccessible during the test window, bridge-based pre-location requiring access to both ends was not feasible. The objective was to locate all fault locations along the buried route and to verify the repaired sheaths through insulation and withstand testing.

Result
All three sheath fault locations were identified during a single site visit: approximately 40 m from the test end on phase A, and approximately 43 m and 90 m on phase C. Following repair of all three locations, the sheath insulation readings returned to normal at 500 V DC, and the outer sheaths of phases A and C passed the DC sheath withstand test.
03  /  Site

Site and Test Conditions

Test location A 330 kV substation cable section.
Cable ends One cable termination on a tower outside the station fence, the other inside the station. The station-side termination was not accessible during the test window.
Installation Direct buried, burial depth under 1 m, route known.
Route condition A busy railway line runs alongside the cable; passing trains produced strong background noise that interfered with acoustic pinpointing.
Customer Anonymized as a power transmission operator.
04  /  Equipment

Equipment Used

Equipment Model Purpose
Insulation resistance tester XHMR-5kV Confirming the sheath-to-ground fault on phases A and C
Sheath fault pinpointing system XHHD523L Step-voltage pinpointing and DC sheath withstand testing
Integrated test system XHHV515-8L Integrated sheath fault location and testing
Multimeter Handheld Continuity and earthing checks before and after testing
05  /  Method

Test Process

01

Insulation assessment and method selection

The test began with an insulation resistance measurement on the outer sheaths of phases A and C at 500 V DC. Both phases gave readings of 0 MΩ to earth, indicating a severe sheath-to-ground fault on each phase. In this case the short cable length, the known route and the limited access to the station-side termination together made direct step-voltage pinpointing a practical choice, so bridge-based pre-location was not required.

latest company case about 330 kV Cable Outer Sheath Fault Location: A and C Phase Sheath Faults on a 100 m Buried Cable  0


02

Phase A pinpointing

The locator was connected between the phase A outer sheath and a remote earth electrode, and the operator walked the route with step-voltage probes. A clear peak in the measured potential gradient was identified at approximately 40 m from the test end; the location was marked and excavated.

latest company case about 330 kV Cable Outer Sheath Fault Location: A and C Phase Sheath Faults on a 100 m Buried Cable  1

03

Phase C pinpointing and the second fault

The same procedure on phase C produced a first clear peak at approximately 43 m. After the first location was excavated and treated, a repeat insulation resistance test still showed a failure on phase C, indicating that an additional fault was present along the cable. The survey continued along the remaining route and identified a second fault location at approximately 90 m. Only after all three locations had been treated did the sheath insulation readings return to normal.

latest company case about 330 kV Cable Outer Sheath Fault Location: A and C Phase Sheath Faults on a 100 m Buried Cable  2

latest company case about 330 kV Cable Outer Sheath Fault Location: A and C Phase Sheath Faults on a 100 m Buried Cable  3

04

Verification by withstand test

The final step was a DC withstand test on the repaired sheaths, using the withstand mode of the same locator. The outer sheaths of phases A and C held the test voltage without breakdown.

06  /  Results

Test Results

The test results are summarised below:

Initial insulation 0 MΩ on the outer sheaths of phases A and C at 500 V DC.
Phase A pinpointing One clear step-voltage peak at approximately 40 m from the test end.
Phase C pinpointing One peak at approximately 43 m; after that location was treated, a repeat insulation test still failed and a second peak was found at approximately 90 m.
Post-repair insulation Readings returned to normal at 500 V DC once all three locations had been treated.
Withstand test The outer sheaths of phases A and C both passed the DC sheath withstand test.
07  /  Verification

Final Diagnosis and Verification

The final diagnosis was one sheath-to-ground fault on phase A and two on phase C; all three locations were pinpointed and subsequently confirmed by excavation. The key evidence was the change in insulation readings before and after repair, together with the successful withstand test. The continued insulation failure after the first phase C fault had been treated indicated that an additional fault remained, and further pinpointing identified the second location at approximately 90 m.

The record covers fault location and the recovery of sheath insulation only. The repair method applied at each excavation, any cable replacement and the re-energisation of the circuit were outside the scope of the report.

08  /  Lessons

Key Takeaways

01

Method selection should follow site conditions, not habit. Here the short cable length, the known route and the limited access to the station-side termination made direct step-voltage pinpointing practical; a longer cable or an accessible far end would have called for a different sequence.

02

For direct-buried sheath faults, step-voltage pinpointing is usually the more reliable option. A high-voltage pulse method often gives little or no audible signal on a shallow sheath, and beside a busy railway the acoustic channel is difficult to use.

03

Re-test after every repair. A repeat insulation test is the quickest way to confirm whether another fault remains — in this case it did, at approximately 90 m.

09  /  Closing

Conclusion

This case demonstrates that selecting the appropriate testing method is more important than simply using more equipment during a sheath fault investigation. The cable was short and only one end could be accessed, so pre-location was not required; the route ran beside a railway, so an acoustic approach would have been unreliable; and the first repair did not restore the insulation, so the survey continued until the second phase C fault was exposed. Insulation testing established the initial fault condition, step-voltage pinpointing identified the fault locations, and the final withstand test provided an additional check of the repaired sheaths.

XZH TEST manufactures cable fault location and sheath testing instruments for transmission and distribution work, including the sheath pinpointing systems used in this survey. If a sheath fault has resisted conventional location, our team can help you choose the right method for the cable length, burial depth and site conditions.

10  /  Compliance

Safety and Compliance Note

Sheath fault location and DC withstand testing involve high voltage and must only be carried out by qualified personnel under an approved work permit. The cable must be isolated, identified, discharged and earthed at both ends before any test connection is made, and the test area must be barricaded. Where the route passes close to railway infrastructure, work must be coordinated with the railway operator.

11  /  FAQ

Frequently Asked Questions

Q1  Why was cable pre-location not used in this case?
Given the short cable length, the known route and the limited access to the station-side termination, the team selected direct step-voltage pinpointing instead of bridge-based pre-location. Bridge-based pre-location would have required access to both cable ends.
Q2  Why did phase C require two excavation points?
The first location at approximately 43 m was treated, but a repeat insulation test still showed a failure, which indicated an additional fault. The survey continued and identified it at approximately 90 m. The insulation readings returned to normal only after both locations had been treated.
Q3  Why was the step-voltage method used instead of a high-voltage pulse method?
The cable is direct buried at less than one metre beside a busy railway. There a high-voltage pulse often produces no audible discharge signal, or one too weak to pinpoint, while the step-voltage gradient remains readable along the surface.
Q4  How was the repaired sheath insulation verified?
The sheath insulation readings returned to normal at 500 V DC, and the outer sheaths of phases A and C passed the DC withstand test. The report does not document subsequent re-energisation of the circuit.
XZH TEST  ·  Cable fault location case record