2026-07-27
Project at a Glance
Client: Jiayu Gulang Huanghuatan 300MW Photovoltaic Power Station
Location: Wuwei, Gansu Province, China
Date: February 23, 2026
Cable Specification: 26/35kV YJLV 3×300mm², 940m total length, direct-buried with joint pits
Fault Type: Flashover-type enclosed fault on Phase A, occurring at 52kV AC withstand voltage after 50 minutes
During the commissioning of the 35kV collector line (Line 35F4) at the Jiayu Gulang Huanghuatan 300MW PV power station, the cable failed its AC withstand voltage test. The cable, connecting Box Transformer No. 08 to tower BJ1 (overhead line transition), experienced a flashover protection trip at 52kV after approximately 50 minutes of testing. Upon re-energization, the voltage could not rise above 7kV, confirming a flashover breakdown on Phase A. With the project on a tight commissioning schedule, rapid fault location and repair were critical to avoid delays in grid connection.
The cable route spanned 940 meters of direct-buried installation with two intermediate joints and terminal joints accessible via dedicated inspection pits. Pre-fault insulation measured R15S: 387GΩ and R60S: 869GΩ (absorption ratio 2.25). Post-flashover readings dropped to 2GΩ with absorption ratio of 1.
| Equipment | Model | Role |
|---|---|---|
| Insulation Resistance Tester | XHMR-5kV | Pre/post-fault insulation diagnosis |
| Cable Fault TDR Tester | 502 | Low-voltage pulse & HV flashover pre-location |
| Acoustic-Magnetic Pinpointer | 503D | Precise fault pinpointing |
| HV Test Transformer & Capacitor | 5-50 + 40/6 | High-voltage pulse generation |
| Burn-Through Bridge | 60Q | Converting flashover to stable low-resistance fault |
| Resonant AC Withstand Test Set | XHBP-1056/528 | Post-repair AC withstand verification |
Using the XHMR-5kV insulation resistance tester, the team confirmed pre-fault insulation at 2.25 absorption ratio and post-flashover readings at 2GΩ with absorption ratio of 1.0, indicating a high-voltage flashover fault requiring elevated test voltage to trigger breakdown.
The 502 TDR tester in low-voltage pulse mode measured the full cable length at 940 meters, revealing joint reflections at approximately 300m and 600m — closely matching field-provided pit locations and narrowing the suspected fault zone.
![]()
![]()
The team deployed the 60Q burn-through bridge, applying a sustained 4kV/10mA current for approximately 10 minutes. Voltage dropped to 0.3kV while current rose above 300mA, confirming the fault point was successfully converted to a stable low-resistance channel suitable for HV flashover testing.
![]()
With the fault channel established, the team configured the 5-50 test transformer with the 40/6 pulse energy storage capacitor for high-voltage flashover testing. The high-voltage output was routed through the discharge ball gap to the faulted phase, with the capacitor ground connected to the cable copper braid shield. The 502 TDR captured flashover waveforms, and analysis determined the fault distance at 317.7 meters from the test terminal.
The 503D acoustic-magnetic pinpointer was deployed near the 317m mark. Joint pits at 300m and 600m yielded no discharge sounds, confirming the fault was not at either joint. At 320m, distinct discharge sounds were detected — faint due to sandy soil dispersal. No visible external damage was found upon excavation, but re-energization revealed localized cable vibration at a specific point. The fault was identified as a factory-made single-phase joint within the cable body, not a field-installed joint.
![]()
After repair, the XHBP-1056/528 variable-frequency series resonant AC withstand test set was used for verification. The cable successfully withstood 52kV AC for 60 minutes, confirming the repair was complete.
940m
Total Cable Length
317.7m
Fault Distance Measured
52kV
Final Withstand Voltage
60min
Post-Repair Test Duration
Insight 1: Cable manufacturers may perform joint-like repairs on damaged sections before factory delivery, creating potential weak points that pass initial visual inspection but fail under sustained AC withstand testing. In this case, the fault originated at a factory-made single-phase joint embedded within the cable body, not at a field-installed joint.
Insight 2: For body faults (not joint faults), cable vibration intensity transmitted through sand or insulating material can serve as an effective secondary pinpointing indicator when acoustic signals from the pinpointer are attenuated by sandy soil conditions.
Insight 3: When a flashover fault cannot be detected by a standard 5000V insulation resistance tester, burn-through treatment is an effective intermediate step. Converting the flashover fault to a stable low-resistance channel significantly improves waveform clarity and distance accuracy in subsequent HV flashover testing.
Your Cable Testing Partner
XZH TEST provides professional cable fault detection equipment and integrated testing solutions for utilities, renewable energy projects, and industrial maintenance teams worldwide. From insulation diagnosis through precise fault pinpointing to post-repair verification, our equipment supports every stage of the cable testing workflow.