logo
Home >

latest company case about Xi'an Xu&Hui Electromechanical Technology Co., Ltd. Certifications

35kV Cable Flashover Fault Detection and Repair at 300MW Wuwei PV Power Station Using Integrated Test System

2026-07-27

latest company case about 35kV Cable Flashover Fault Detection and Repair at 300MW Wuwei PV Power Station Using Integrated Test System

Project at a Glance

Client: Jiayu Gulang Huanghuatan 300MW Photovoltaic Power Station

Location: Wuwei, Gansu Province, China

Date: February 23, 2026

Cable Specification: 26/35kV YJLV 3×300mm², 940m total length, direct-buried with joint pits

Fault Type: Flashover-type enclosed fault on Phase A, occurring at 52kV AC withstand voltage after 50 minutes

Project Background

During the commissioning of the 35kV collector line (Line 35F4) at the Jiayu Gulang Huanghuatan 300MW PV power station, the cable failed its AC withstand voltage test. The cable, connecting Box Transformer No. 08 to tower BJ1 (overhead line transition), experienced a flashover protection trip at 52kV after approximately 50 minutes of testing. Upon re-energization, the voltage could not rise above 7kV, confirming a flashover breakdown on Phase A. With the project on a tight commissioning schedule, rapid fault location and repair were critical to avoid delays in grid connection.

The cable route spanned 940 meters of direct-buried installation with two intermediate joints and terminal joints accessible via dedicated inspection pits. Pre-fault insulation measured R15S: 387GΩ and R60S: 869GΩ (absorption ratio 2.25). Post-flashover readings dropped to 2GΩ with absorption ratio of 1.

Equipment Deployed

Equipment Model Role
Insulation Resistance Tester XHMR-5kV Pre/post-fault insulation diagnosis
Cable Fault TDR Tester 502 Low-voltage pulse & HV flashover pre-location
Acoustic-Magnetic Pinpointer 503D Precise fault pinpointing
HV Test Transformer & Capacitor 5-50 + 40/6 High-voltage pulse generation
Burn-Through Bridge 60Q Converting flashover to stable low-resistance fault
Resonant AC Withstand Test Set XHBP-1056/528 Post-repair AC withstand verification

Testing Process

Step 1 — Insulation Diagnosis & Fault Nature Assessment

Using the XHMR-5kV insulation resistance tester, the team confirmed pre-fault insulation at 2.25 absorption ratio and post-flashover readings at 2GΩ with absorption ratio of 1.0, indicating a high-voltage flashover fault requiring elevated test voltage to trigger breakdown.

Step 2 — Cable Length Measurement & Joint Identification

The 502 TDR tester in low-voltage pulse mode measured the full cable length at 940 meters, revealing joint reflections at approximately 300m and 600m — closely matching field-provided pit locations and narrowing the suspected fault zone.

latest company case about 35kV Cable Flashover Fault Detection and Repair at 300MW Wuwei PV Power Station Using Integrated Test System  0latest company case about 35kV Cable Flashover Fault Detection and Repair at 300MW Wuwei PV Power Station Using Integrated Test System  1

Step 3 — Burn-Through Treatment

The team deployed the 60Q burn-through bridge, applying a sustained 4kV/10mA current for approximately 10 minutes. Voltage dropped to 0.3kV while current rose above 300mA, confirming the fault point was successfully converted to a stable low-resistance channel suitable for HV flashover testing.

latest company case about 35kV Cable Flashover Fault Detection and Repair at 300MW Wuwei PV Power Station Using Integrated Test System  2

Step 4 — High-Voltage Flashover Pre-Location

With the fault channel established, the team configured the 5-50 test transformer with the 40/6 pulse energy storage capacitor for high-voltage flashover testing. The high-voltage output was routed through the discharge ball gap to the faulted phase, with the capacitor ground connected to the cable copper braid shield. The 502 TDR captured flashover waveforms, and analysis determined the fault distance at 317.7 meters from the test terminal.

Step 5 — Precise Acoustic-Magnetic Pinpointing

The 503D acoustic-magnetic pinpointer was deployed near the 317m mark. Joint pits at 300m and 600m yielded no discharge sounds, confirming the fault was not at either joint. At 320m, distinct discharge sounds were detected — faint due to sandy soil dispersal. No visible external damage was found upon excavation, but re-energization revealed localized cable vibration at a specific point. The fault was identified as a factory-made single-phase joint within the cable body, not a field-installed joint.

latest company case about 35kV Cable Flashover Fault Detection and Repair at 300MW Wuwei PV Power Station Using Integrated Test System  3

Step 6 — Repair & Verification

After repair, the XHBP-1056/528 variable-frequency series resonant AC withstand test set was used for verification. The cable successfully withstood 52kV AC for 60 minutes, confirming the repair was complete.

Key Results

940m

Total Cable Length

317.7m

Fault Distance Measured

52kV

Final Withstand Voltage

60min

Post-Repair Test Duration

Technical Insights

Insight 1: Cable manufacturers may perform joint-like repairs on damaged sections before factory delivery, creating potential weak points that pass initial visual inspection but fail under sustained AC withstand testing. In this case, the fault originated at a factory-made single-phase joint embedded within the cable body, not at a field-installed joint.

Insight 2: For body faults (not joint faults), cable vibration intensity transmitted through sand or insulating material can serve as an effective secondary pinpointing indicator when acoustic signals from the pinpointer are attenuated by sandy soil conditions.

Insight 3: When a flashover fault cannot be detected by a standard 5000V insulation resistance tester, burn-through treatment is an effective intermediate step. Converting the flashover fault to a stable low-resistance channel significantly improves waveform clarity and distance accuracy in subsequent HV flashover testing.

Your Cable Testing Partner

XZH TEST provides professional cable fault detection equipment and integrated testing solutions for utilities, renewable energy projects, and industrial maintenance teams worldwide. From insulation diagnosis through precise fault pinpointing to post-repair verification, our equipment supports every stage of the cable testing workflow.