2026-07-23
Project: Tongchuan Huangbao Town QinYuan PV Station 800V Low-Voltage Cable Fault Detection
Test Personnel: Ge Haojie, Qiao Yifan, Gao Fei | Date: June 9-10, 2026
The QinYuan Photovoltaic Station in Huangbao Town, Tongchuan, experienced an operational outage on one of its 800V low-voltage collector cables connecting a transformer to the PV array inverters. The site engineering team requested professional cable fault detection services to locate and identify the fault, enabling targeted excavation and repair with minimal impact on power generation.
| Site Parameter | Details |
|---|---|
| Cable Type | YJLV-3×120 (Aluminum conductor, XLPE insulated, PVC sheathed) |
| Cable Length | Approximately 260 meters |
| Operating Voltage | 800V DC / Low-voltage AC |
| Routing | Transformer → buried path → PV array inverters; cables intact, armor bonding properly grounded |
| Site Conditions | Nearby inverters continuously operating, generating strong electromagnetic interference |
Initial insulation resistance measurements were conducted using a 1000V megohmmeter across all three phases (A, B, C) referenced to the cable armor:
| Test Point | Result |
|---|---|
| Phase A to Armor | >1 GΩ — healthy, no insulation degradation detected |
| Phase B to Armor | 0 Ω — direct short circuit confirmed; digital multimeter measured 24Ω on resistance range, continuity mode indicated conduction |
| Phase C to Armor | >1 GΩ — healthy, no insulation degradation detected |
Fault Nature Confirmed: Single-phase (B-phase) low-resistance short circuit to cable armor. The 24Ω resistance value classified this as a low-resistance fault rather than a dead short, which would later prove significant for acoustic pinpointing difficulty.
Fault distance pre-location was performed using the low-voltage pulse reflection method (TDR). A low-voltage pulse was injected into the B-phase conductor from both cable ends to cross-validate the fault distance measurement:
| Test Direction | Measured Distance to Fault |
|---|---|
| From Transformer End (LV distribution cabinet) | 185 meters |
| From PV Inverter End (reverse verification) | 85 meters |
| Total Cable Length (verified) | 260 meters (185m + 85m ≈ 260m — cross-validation consistent) |
The low-voltage pulse waveform clearly displayed the fault reflection point, with the total cable length waveform confirming the 260m overall distance. The bi-directional measurements yielded consistent results: 185m from the transformer side and 85m from the inverter side, with the combined distances matching the known cable length — confirming the pre-location accuracy.
Fault pinpointing was attempted using the XHHV515-8L high-voltage pulse generator in conjunction with an operating control box and test transformer. Based on the pre-location results, the fault was approximately 85m from the inverter end. However, several field conditions complicated the acoustic-magnetic pinpointing process:
Given the acoustic-magnetic method limitations under the site conditions, the team deployed the XHHV507 pipeline and cable locator in audio frequency mode as an alternative pinpointing technique:
| Instrument | Role in Fault Detection Process |
|---|---|
| XHGG502 Cable Fault Locator (TDR) | Low-voltage pulse pre-location — cable length measurement and fault distance determination |
| 503 / 503C / 503E Series | Supplementary fault pre-location and waveform analysis |
| XHGX507 Pipeline & Cable Locator | Audio frequency cable tracing and fault point identification under inverter interference conditions |
| XHHV515-8L HV Pulse Generator | High-voltage impulse discharge for acoustic-magnetic fault pinpointing |
| Operation Box + Test Transformer (5/50) | High-voltage power supply and control for impulse discharge system |
| Pulse Energy Storage Capacitor (40/6) | Energy storage for high-voltage impulse discharge |
| 515-8L Insulation Resistance Tester | Pre-test cable insulation assessment (1000V megohmmeter range) |
| Digital Multimeter | Resistance measurement and continuity verification (24Ω fault confirmation) |
| Finding | Detail |
|---|---|
| Fault Type | B-phase low-resistance short circuit to cable armor (24Ω) |
| Fault Location | 85m from PV inverter end / 185m from transformer end — confirmed by bi-directional TDR and audio frequency tracing |
| Probable Cause | Insulation damage at a single point on B-phase conductor, likely from external mechanical stress or manufacturing defect manifesting under thermal cycling during station operation |
| Repair Action | Excavate at identified location (85m from inverter end), expose cable, cut out damaged section, install inline cable joint with proper insulation restoration and armor rebonding |