A 10 kVA oil-immersed test set for cable and transformer insulation, combining 50 kV AC withstand testing with 70 kV DC leakage testing in one transportable unit.
After a joint or a repair, the cable insulation is proved by raising the voltage to the specified level and holding it for the required time. The 50 kV AC output covers 10 kV and 35 kV cable classes. The same set can then be switched to DC for a leakage current reading on the same cable, which shows whether the insulation is stable or drawing increasing current.
Distribution transformer windings, bushings and motor coils are tested at power frequency to prove insulation strength. The 10 kVA rating is matched to the charging current of these specimens, and the 30-minute duty allows a complete test sequence without waiting for the set to cool between small units.
The control box is connected to the transformer primary, the high-voltage lead goes to the specimen, and the earth terminal is bonded to the station earth. The specimen is discharged and earthed with a discharge rod before any lead is touched. The manual also calls for screened leads in DC tests to avoid stray leakage affecting the reading.
The voltmeter shows the applied voltage and the DC microammeter shows leakage current directly during a DC test. The voltage, current and test time are written into the record together with the cable or winding temperature, because a reading taken cold is not directly comparable with one taken after loading.
| Mode | Output voltage | Output current | Capacity | Input | Ratio | Temp rise |
|---|---|---|---|---|---|---|
| AC | 50 kV | 200 mA | 10 kVA | 220/380 V, 50/26 A | 500 | 10 C / 30 min |
| DC | 70 kV | 100 mA | - | 380 V, 50/26 A | 500 | 10 C / 30 min |
The 50 kV AC output covers 10 kV and 35 kV cable classes. The test voltage and hold time come from the standard applied on site, not from the set rating alone.
The rated duty is 30 minutes, with a winding temperature rise of 10 C. Small specimens can be tested in sequence within that window.
Yes. The cable or winding is discharged and earthed with a discharge rod after the test, before leads are removed or the specimen is touched.
Send the cable class, length and conductor size, and we will confirm that the 50 kV AC and 70 kV DC outputs cover the test list.
Overall Rating
Rating Snapshot
The following is the distribution of all ratingsAll Reviews